We delivered the boiler plant as consortium leader under an EPC contract, from the first drawing and site scan all the way to operator training.
Design took us 130 days, construction took 270 and commissioning and testing another 104. We kept to the schedule, and on 24 September 2026 we handed the plant over for trial operation, which is now running under real conditions in its first heating season.
The boiler plant serves as the backup and peak-load source for ČEZ’s new low-emission heating plant, which has been supplying heat to 15,000 households in Orlová and Bohumín since the start of this season. The heating plant replaced a coal-fired power station and cuts emissions by up to 97%.
Many thanks to ČEZ Teplárenská for their trust and to our partners for their cooperation.
How Dětmarovice said goodbye to coal, and what the new heating plant includes, is described in the ČEZ press release.